POSTED 4:55 PM PST, Friday, January 03, 2014 

McDowell Ave Overnight Closures, Jan 6 & 7

There will be nighttime closures of McDowell Avenue from 9:30 p.m. to 5:30 a.m. the following morning on January 6 & 7 as construction of the Northbound High Viaduct continues near the roadway. This work is necessary to complete a temporary realignment of McDowell Avenue that will make room for temporary supports (falsework) for future construction of the Northbound High Viaduct.

Due to ongoing bridge construction in this area, drivers should expect intermittent delays and increased truck traffic.

For more information, including a map of detours during construction, view the construction advisory.


POSTED 3:27 PM PST, Wednesday, December 11, 2013 

Lane Closures, Night Work & Alignment Shift on Highways 1 & 101, December 11-15

Beginning on December 11 for approximately 5 days there will be night work and lane closures along north and southbound Highways 1 and 101. The night work is expected to occur Wednesday through Sunday night to prepare to shift traffic lanes slightly to the south in order to continue work on the northbound shoulder. 

Activity on Wednesday and Thursday nights is expected to occur primarily near the toll plaza to drill holes for the new pylon locations. Friday, Saturday and Sunday work will include grinding out existing lane striping and restriping the lanes along Highways 1 and 101. Traffic is expected to be on the new, temporary alignment beginning Monday.

Please view the advisory for further information.


POSTED 2:31 PM PST, Wednesday, November 20, 2013 

One-Way Traffic Control on Lincoln Blvd near Sheridan Ave. on Nov. 20 & 21
On Wednesday, November 20 and Thursday, November 21, from 7:00 a.m. - 6:00 p.m., there will be one-way traffic control on Lincoln Boulevard near Sheridan Avenue.
 
Traffic control is needed to provide room for construction near the southbound Battery Tunnel adjacent to Lincoln Boulevard and the San Francisco National Cemetery. 
 
Expect minor delays during this activity.

On Wednesday, November 20 and Thursday, November 21, from 7:00 a.m. - 6:00 p.m., there will be one-way traffic control on Lincoln Boulevard near Sheridan Avenue. Traffic control is needed to provide room for construction near the southbound Battery Tunnel adjacent to Lincoln Boulevard and the San Francisco National Cemetery. Expect minor delays during this activitOn Wednesday, November 20 and Thursday, November 21, from 7:00 a.m. - 6:00 p.m., there will be one-way traffic control on Lincoln Boulevard near Sheridan Avenue. Traffic control is needed to provide room for construction near the southbound Battery Tunnel adjacent to Lincoln Boulevard and the San Francisco National Cemetery. Expect minor delays during this activity.


POSTED 3:53 PM PST, Friday, November 15, 2013 

North Fort Scott and Pilots' Row Neighborhood Update, November 15
Thank you for your patience and cooperation during recent tree pruning/removals in your neighborhood. Professional Tree Care has wrapped up work in the interior residential portion of your neighborhood, and will move across Armistead Road to complete pruning on the southern/western side of the street. The pruning/removals southwest of Armistead are expected to begin the week of November 18 and will take approximately 3 weeks. This will conclude tree work staged from within the neighborhood. 

Thank you for your patience and cooperation during recent tree pruning/removals in your neighborhood. Professional Tree Care has wrapped up work in the interior residential portion of your neighborhood, and will move across Armistead Road to complete pruning on the southern/western side of the street. The pruning/removals southwest of Armistead are expected to begin the week of November 18 and will take approximately 3 weeks. This will conclude tree work staged from within the neighborhood.

 


POSTED 2:04 PM PST, Tuesday, November 05, 2013 

Lane Closures & Night Work on SB Hwy 1/101 to Begin November 6
On November 6, November 7, and November 12 - November 15, there will be night work and lane closures along southbound Highway 1/101 for roadway widening. The lane closures are scheduled from 9:00 p.m. to 4:30 a.m. the next morning. This work may continue into the week of November 18.

View the advisory for further information.


POSTED 1:38 PM PST, Friday, October 25, 2013 

Night Work and Truck Hauling, October 2013
In the coming weeks, there will be night work associated with Highway 1/101 realignment and construction of the Main Post Tunnels. Night work for the Main Post Tunnels will include excavation, storing, and off-hauling of soil, as well as materials delivery, including base rock material and concrete



POSTED 2:36 PM PST, Tuesday, October 15, 2013 

Construction Update, October 2013
Construction of the Presidio Parkway is going full speed ahead! Much of the work can be seen from Doyle Drive and the Presidio: Building 201 has been moved, tunnel excavation is under way, and Highways 1 and 101 are being realigned between the Golden Gate Bridge Toll Plaza and the interchange.

For more information, read the full Construction Update.


POSTED 12:54 PM PST, Thursday, October 10, 2013 

Project Update in the Marin Independent Journal
Check out the recent story in the Marin Independent Journal for a project update and a glimpse of what is to come for the Presidio:   http://www.marinij.com/goldengatebridge/ci_24276873/doyle-drive-now-gone-marin-commuters-see-changes



POSTED 12:01 PM PST, Friday, October 04, 2013 

Upcoming Night Work Along NB Hwy 1 to Hwy 101, Oct. 2013
There will be intermittent night work along the connector ramp from northbound Highway 1 to Highway 101 during the weeks of October 7th and October 14th. This work requires a lane closure on northbound Highway 1 and is scheduled to occur between 9 p.m. and 7 a.m. the following day. During the lane closure, crews will place the roadway base and pavement to temporarily realign Highway 1/101.

Drivers can expect to experience shifting road alignments as construction progresses in the corridor. There will continue to be intermittent lane closures and night work in this area.

Please view the project advisory for further information.


POSTED 2:41 PM PST, Monday, September 16, 2013 

Tree Pruning and Removal on Armistead Rd. and Ramsel Ct. to begin September 23
On Monday, September 23, tree pruning and select removal is scheduled to begin within the neighborhood on Armistead Road and Ramsel Court. The pruning and removal activity is expected to last approximately six weeks and is in preparation for more extensive tree removal between Armistead Road and northbound Highway 101 (NB 101). A subsequent advisory will be circulated about the tree removal along NB 101 when the schedule is confirmed.

Direct coordination will occur with the tenants who have reserved spaces impacted by this work.

Please view the project advisory for further information.

Please view the work plan for more specific information about projected sequence, staging, and parking impacts.


POSTED 1:53 PM PST, Friday, September 06, 2013 

Extended Hours in Cavalry Bowl, September 2013
There will be intermittent work occurring outside of normal work hours to allow construction of the foundations and columns for the future northbound High Viaduct. These extended hours are required for continuous construction activities, such as large concrete pours. Oversized equipment deliveries will also occur outside of normal work hours throughout project construction.

For more information, read the construction advisory.


POSTED 4:16 PM PST, Tuesday, September 03, 2013 

Parking Area behind Gorgas Warehouses to Close, Week of September 9
 

In order to make room for the future low viaducts 
and direct access to the Presidio, the parking area 
behind the Gorgas Warehouses will close the week of 
September 9. 
Beginning the week of September 2, work crews 
will begin installing a fence to delineate the future 
emergency vehicle access lane behind the Gorgas 
Warehouses. You will begin to see increased activity 
in the area including, Concrete Deep Soil Mixing 
for ground stabilization and then installation of 
foundations for the future low viaducts.
 

In order to make room for the future low viaducts and direct access to the Presidio, the parking area behind the Gorgas Warehouses will close the week of September 9. 

Beginning the week of September 2, work crews will begin installing a fence to delineate the future emergency vehicle access lane behind the Gorgas Warehouses. You will begin to see increased activity in the area including, Concrete Deep Soil Mixing for ground stabilization and then installation of foundations for the future low viaducts.

View the advisory for a map of the work area.


POSTED 12:22 PM PST, Wednesday, August 28, 2013 

Meeting Materials for North Fort Scott/Pilots' Row Meeting, August 22, 2013
The project team hosted a neighborhood meeting and site walk for residents to learn about upcoming construction activity near the North Fort Scott and Pilots' Row neighborhoods. The project construction manager and arborist provided details of nearby Phase II activity including the realignment of the Highway 1/101 interchange, the sequence of work, overall schedule, tree pruning and removals, the anticipated impacts of construction, and preliminary landscaping concepts.

Materials from this meeting are posted below.

View the meeting materials packet.

View the altered stand assessment.


POSTED 1:51 PM PST, Thursday, August 15, 2013 

Construction Update, August 2013
Construction of the Presidio Parkway is going full speed ahead! Much of the work can be seen from Doyle Drive and the Presidio: the old High Viaduct has been demolished, Building 201 has been moved to clear the way for tunnel construction, and tunnel excavation is under way.

Keep an eye on Doyle Drive, the transformation of the Presidio waterfront is in full swing!

For more information, read the Construction Update.


POSTED 9:56 AM PST, Monday, July 22, 2013 

24 Hour Concrete Deep Soil Mixing
 

In order to expedite construction and take advantage of the dry season, crews will be conducting concrete deep soil mixing (CDSM) near the Main Post 24 hours a day beginning the week of July 8.

CDSM is a construction method being used to stabilize soil beneath the future roadway and Main Post Tunnels. The equipment penetrates the ground surface and combines cement and water, digging up to 60 feet into the ground. The result is a soil/cement mixture that creates a grid of improved, stable soil to prevent settlement or liquefaction during a seismic event.

This work is expected to continue 24 hours a day for several months. Additional activities that may require extended work hours include tunnel excavation, concrete pours, and continuous drilling.

View the project advisory for a map of the 24 hour work area.

 


POSTED 1:58 PM PST, Friday, June 28, 2013 

McDowell Ave. Overnight Closures, July 1 - 3, 2013
There will be nighttime closures of McDowell Avenue from 9:30 p.m. to 5:30 a.m. the following morning on July 1 - 3 as high viaduct removal continues near the roadway.  

During these closures, crews will demolish the final pieces of the column that is closest to McDowell.  Work will be noisy as heavy equipment removes the concrete and steel columns adjacent to the roadway.  

Crews finished work earlier than expected near Lincoln Boulevard. Activity requiring overnight closures on Lincoln Boulevard is expected to wrap up the morning of June 29.

Please see the advisory for further information.


POSTED 3:16 PM PST, Wednesday, June 26, 2013 

Update for North Fort Scott and Pilots' Row Residents
 

Phase II of construction on the Presidio Parkway project includes significant changes at the west end of the project area. Work near the North Fort Scott & Pilots' Row neighborhood will include the realignment of Highway 1/Highway 101 between the toll plaza and the interchange, as well as construction of the hook ramp from northbound Doyle Drive/Highway 101 to southbound 19th Ave/Highway 1.

 The project team is planning a neighborhood meeting/site walk for North Fort Scott and Pilot’s Row residents to discuss nearby Phase II activity including the sequence of work, overall schedule, tree removals, the anticipated impacts of construction, and future landscaping concepts. In an effort to provide detailed and accurate construction information, this meeting is expected to occur in late July.

The project team will set a date for the meeting based on the ongoing evaluation of construction phasing and the arborists’ assessment of the extent of tree removals that will be required based on the roadway realignment. The earliest tree removal will occur is September 2013 and the specific timing and schedule is still being determined.

Please sign up to receive future advisories and updates:  http://presidioparkway.org/contact/

 


POSTED 2:00 PM PST, Friday, June 21, 2013 

Lincoln Blvd. Night Closures, Beginning June 24
Lincoln Boulevard will be CLOSED weekdays from 9:30 p.m. to 5:30 a.m. the next morning from Tuesday, June 24 through Tuesday, July 9 (excluding July 4 & 5).  This closure is required as deconstruction of the steel truss of the old High Viaduct occurs over Lincoln Boulevard.

The bike path adjacent to Lincoln Boulevard (Presidio Promenade) will also be closed during this time.


POSTED 11:03 AM PST, Tuesday, May 21, 2013 

Traffic Control, Expect Delays on Mason St.
 

Utility installation and relocation is underway to prepare for the second phase of Presidio Parkway construction. Beginning the week of May 13 and continuing for approximately one month, there will 
be intermittent traffic control on Mason Street and minor parking impacts east of the Sports Basement. Please watch for “No Parking” signs, detour signs and traffic flaggers.
Utility installation and relocation is underway to prepare for the second phase of Presidio Parkway construction. Beginning the week of May 13 and continuing for approximately one month, there will be intermittent traffic control on Mason Street and minor parking impacts east of the Sports Basement. Please watch for “No Parking” signs, detour signs and traffic flaggers.

 

Please see the advisory for further information.


POSTED 12:18 PM PST, Thursday, May 16, 2013 

McDowell Ave Night Closures, Beginning May 16
McDowell Avenue will be CLOSED from 9:30 p.m. to 5:30 a.m. the next morning Monday through Friday for approximately two weeks, beginning Thursday, May 16.

This closure is required as deconstruction of the old High Viaduct continues over McDowell Avenue. The work will include demolishing the steel truss and columns.

See the advisory for a map of detours during McDowell Avenue closures.

Beginning the week of May 13 and continuing for approximately one month, there will be intermittent traffic control on Mason Street and minor parking impacts east of the Sports Basement. This work is required as part of ongoing utility installation and relocation. Please watch for “No Parking” signs, detour signs and traffic flaggers.

View the Mason Street advisory for additional information.


POSTED 4:59 PM PST, Monday, May 13, 2013 

Lincoln Blvd Nighttime Closures, May 13 & 14
 

Lincoln Boulevard will be CLOSED from 10:00 p.m. to 5:00 a.m. the next morning on Monday, May 13 and potentially on Tuesday, May 14 from 10:00 p.m. to 2:00 a.m. This closure is required as deconstruction of the old High Viaduct occurs over Lincoln Boulevard.
Work hours will be 9:30 p.m. to 5:30 a.m. The work includes demolishing the roadway deck and removing steel girders.
Lincoln Boulevard will be CLOSED from 10:00 p.m. to 5:00 a.m. the next morning on Monday, May 13 and potentially on Tuesday, May 14 from 10:00 p.m. to 2:00 a.m. This closure is required as deconstruction of the old High Viaduct occurs over Lincoln Boulevard.

Work hours will be 9:30 p.m. to 5:30 a.m. The work includes demolishing the roadway deck and removing steel girders.

 


POSTED 3:14 PM PST, Thursday, May 02, 2013 

Lincoln Blvd Night Closures, May 6-10
 

Lincoln Boulevard will be CLOSED from 10:00 p.m. to 5:00 a.m. the next morning from Monday, May 6 through Friday, May 10. This closure is required as deconstruction of the old High Viaduct occurs over Lincoln Boulevard. 

Work hours will be 9:30 p.m. to 5:30 a.m. The work includes demolishing the roadway deck and removing steel girders. The bike path adjacent to Lincoln Boulevard (Presidio Promenade) will also be closed during this time.
Lincoln Boulevard will be CLOSED from 10:00 p.m. to 5:00 a.m. the next morning from Monday, May 6 through Friday, May 10. This closure is required as deconstruction of the old High Viaduct occurs over Lincoln Boulevard. 

Work hours will be 9:30 p.m. to 5:30 a.m. The work includes demolishing the roadway deck and removing steel girders. The bike path adjacent to Lincoln Boulevard (Presidio Promenade) will also be closed during this time.

 


POSTED 1:30 PM PST, Thursday, April 18, 2013 

Gorgas Warehouses Parking Area Closed – April 22
 

The parking lot behind the Gorgas Warehouses will be closed for underground utility installation. The work includes removing pavement (saw cutting and jackhammering), digging trenches, installing utilities, replacing and compacting soil and paving. This work is expected to last approximately 3 weeks.

All businesses remain open.Thank you for your patience.
The parking lot behind the Gorgas Warehouses will be closed beginning April 22 for underground utility installation. The work includes removing pavement (saw cutting and jackhammering), digging trenches, installing utilities, replacing and compacting soil and paving. This work is expected to last approximately 3 weeks.

All businesses remain open. Thank you for your patience.

See the advisory for a map of the closure.

 


POSTED 10:51 AM PST, Friday, April 12, 2013 

McDowell Avenue Night Closures, April 15-19
 

McDowell Avenue will be CLOSED from 9:30 p.m. to 5:30 a.m. the next morning beginning Monday, April 8 through Friday, April 12. 

This closure is required for deconstruction of the old High Viaduct to occur over the roadway. 

The work includes demolishing the roadway deck and removing steel girders.

View the advisory for additional information.
McDowell Avenue will be CLOSED from 9:30 p.m. to 5:30 a.m. the next morning beginning Monday, April 15 through Friday, April 19. 

This closure is required for deconstruction of the old High Viaduct to occur over the roadway. 

The work includes demolishing the roadway deck and removing steel girders.

View the advisory for additional information.

 


POSTED 3:03 PM PST, Friday, April 05, 2013 

McDowell Ave Night Closures, April 8-12, 9:30pm - 5:30am
McDowell Avenue will be CLOSED from 9:30 p.m. to 5:30 a.m. the next morning beginning Monday, April 8 through Friday, April 12.

This closure is required for deconstruction of the old High Viaduct to occur over the roadway. 

The work includes demolishing the roadway deck and removing steel girders.

View the advisory for additional information.


POSTED 10:34 AM PST, Wednesday, March 27, 2013 

Temporary Pump Station to be Removed
Beginning the week of March 25, the temporary pump station on Lincoln Boulevard will be removed and the sidewalk will be restored. Access from Riley Avenue and the Taylor Road parking area will be from Sheridan Avenue. Work is scheduled to begin at 7 AM. Please follow the direction of flaggers and signage.This work will include pavement and utility removal and requires the use of heavy equipment. Removal of the pump station is expected to last approximately two weeks.


POSTED 4:26 PM PST, Thursday, November 15, 2012 

Parking Spaces Removed Behind Swords to Plowshares, November 19
As part of the beginning of Phase II construction of the Presidio Parkway, crews will be adjusting the fence line around the project site to make room for additional construction staging areas.

On Monday, November 19, the fence line behind Swords to Plowshares will be moved to the south, which will remove one row of parking in the area. Parking restriction signage will be posted in advance of this work.

The row of parking closest to Swords to Plowshares will remain in place.

See the advisory for a map of the parking spaces removed.


POSTED 3:51 PM PST, Wednesday, September 12, 2012 

Final Portion of Lincoln Blvd to be Paved and Open Soon!
A section of Lincoln Boulevard as well as a new multi-use trail connecting Montgomery Street and Sheridan Avenue will be paved on September 13 and 14.

Please note that the temporary utility station (in the fenced enclosure near Sheridan) will constrict the pathway when the path is initially opened. When the permanent facility is completed in the Cavalry Stables area, the temporary utility station along this segment of Lincoln will be removed from this area and the full width path will be paved to Sheridan at that time.

View the construction advisory for more information.

 


POSTED 8:06 AM PST, Thursday, July 26, 2012 

Night Work for Concrete Pour, July 27
On Friday, July 27 from 9:00 p.m. to 6:00 a.m. the next morning there will be night work on the northbound side of the temporary bypass to pour concrete for a section of pavement. Work will include concrete trucks and the use of back-up beepers and lights. This work requires lane closured on northbound Doyle Drive and must occur at night to reduce traffic impacts. Additionally, work is underway to restore Lincoln Boulevard and the multi-use trail between Sheridan Avenue and Montgomery Street. The road and trail are expected to be open in early September.


POSTED 1:46 PM PST, Friday, June 22, 2012 

Building 230 Deconstruction
Beginning the week of June 18, crews started deconstruction of Building 230 in the Presidio, the former Archaeology Lab building. This work is a first step to clear the way for future construction at the eastern end of the Presidio Parkway. This is the first of several buildings to be removed to make room for the new roadway. Reusable materials from Building 230 will be salvaged for use by the Presidio Trust on restoration projects throughout the park. The deconstruction of Building 230 will take approximately one month. View the advisory for additional information.


POSTED 12:33 PM PST, Tuesday, June 19, 2012 

Night Work for Lane Striping, June 20
On Wednesday, June 20 from 9 pm to 5 am the next morning there will be minor night work along southbound Highway 101/Doyle Drive. This work is in preparation for upcoming lane restriping in order to improve the alignment of the roadway.

This work requires lane closures along southbound Highway 101 and must occur at night to reduce traffic impacts.


POSTED 2:12 PM PST, Tuesday, May 29, 2012 

Night Work for Utility Cutover
On Friday, June 1 from 7:00 p.m. to 5:00 a.m. the next morning, crews will be working near Riley Avenue to conduct an electrical utility cutover. Work will include use of heavy machinery, chipping of concrete and the use of a generator.

Power outages associated with this work will not affect residents. The cutover is scheduled to occur at night to reduce impacts to commercial tenants.

For additional information, view the neighborhood letter.


POSTED 8:48 AM PST, Sunday, April 22, 2012 

Night Work Along NB Doyle Drive, April 22-26
Beginning Sunday, April 22 through Thursday, April 26 there will be night work along northbound Doyle Drive near the Riley Avenue neighborhood. Work hours on Sunday will be 9:00 p.m. to noon the next day. Work hours on Monday - Thursday will be 8:00 p.m. to noon the next day.
 
During the night work, crews will remove the sidewalk along the northbound side of Doyle Drive, which will include sawcutting and the use of heavy machinery and is expected to be noisy. See the full advisory about this work for more information.

 
The night work requires the closure of the Marina ramp to and from Doyle Drive and must occur at night to reduce traffic impacts.
 
This work is in preparation for the weekend closure of Doyle Drive which will begin at 8:00 p.m. on Friday, April 27. Demolition activities will last throughout the weekend and will be noisy! If possible, Riley residents may wish to find alternate places to stay until work is done the morning of April 30.


POSTED 7:09 AM PST, Tuesday, April 17, 2012 

Night Work – Hwy 1/101 Lane Closures, April 16
On Monday, April 16 there will be night work on and around the Ruckman Bridge and along southbound Highway 101. The work requires lane closures on Highway 1 and southbound Highway 101 and therefore must occur at night.

Work will include roadway repair and the use of heavy machinery.

Work hours will be from 9:00 p.m. to 4:00 a.m.


POSTED 8:27 AM PST, Friday, April 06, 2012 

Bus Parking Lot Closing, April 6, 2012
On Friday, April 6, the bus parking area and one row of vehicle parking behind the Swords to Plowshares building will close. This area will be used for construction staging, equipment, and a temporary command center for the upcoming weekend closure.

Access to the remaining parking spaces and Girard Road will be maintained.

See the advisory for a map of the lot closure.


POSTED 2:11 PM PST, Thursday, March 22, 2012 

Eight Parking Spaces Removed Behind Building 1188, Beginning March 26
Beginning Monday, March 26, eight parking spaces behind Building 1188 and the sidewalk adjacent to Doyle Drive will be permanently removed. This work is needed to prepare for the upcoming demolition of Doyle Drive and the traffic shift onto the temporary bypass for the Presidio Parkway project, expected to occur in the coming months.

Work will include removal of the sidewalk and pavement behind the parking lot, which is expected to be noisy and will include the use of jackhammers and heavy equipment. The demolition activity is expected to last approximately one week during this three week project.

Activity will occur during daytime hours, generally from 7:00 a.m. to 4:00 p.m. The schedule could be delayed due to rain. Please visit our website for updates on the project schedule.

View the advisory for work locations and parking impacts.


POSTED 12:44 PM PST, Monday, March 19, 2012 

Night Work – Hwy 1/101 Lane Closures
Beginning Tuesday, March 20 through Thursday, March 22 there will be night work on and around the Ruckman Bridge and along southbound Highway 101. The work requires lane closures on Highway 1 and southbound Highway 101 and therefore must occur at night.

Work will include installation of light poles and signage, hydroseeding, and application of anti-graffiti coating on roadway structures.

Work hours will vary each night depending on the specific activities; the longest work hours will be from 8:00 p.m. to 7:00 a.m.


POSTED 4:53 PM PST, Tuesday, March 06, 2012 

Night Work Beginning March 6
Beginning Tuesday, March 6 through Friday, March 9 there will be night work on and around the Ruckman Bridge and along southbound Highway 101. The work requires lane closures on Highway 1 and southbound Highway 101 and therefore must occur at night.

Details for the night work are:
Tuesday, March 6: temporary barrier rail (k-rail) replacement along NB and SB Hwy 1
Wednesday, March 7: electrical work along SB Hwy 101
Thursday, March 8: electrical work along SB Hwy 101 and installation of directional signage along Hwy 1 and Hwy 101
Friday, March 9: hydroseeding along SB Hwy 101 and additional signage installation

Work hours will vary each night depending on the specific activities; the longest work hours will be from 8:00 p.m. to 7:00 a.m.


POSTED 5:33 PM PST, Friday, February 24, 2012 

Night Work – Hwy 1 Lane Closures
Beginning Friday, February 24 through next week, there will be night work on and around the Ruckman Bridge, and along southbound Highway 101. The work requires lane closures on Highway 1 and southbound Highway 101 and therefore must occur at night.

The work will include installation of light poles, electronic signs, highway signs, erosion control, moderate paving and connecting electrical systems.

Night work hours will vary depending on the activity and lane closure restrictions. The longest work hours will be between 10:00 p.m. and 7:00 a.m.


POSTED 2:22 PM PST, Tuesday, February 21, 2012 

Night Work, Tuesday, February 21
There will be night work Tuesday, February 21 from 10:00 p.m. to 7:00 a.m. along northbound and southbound Highway 1 at the Highway 101 interchange. Work along northbound Highway 1 will include drainage inlet installation, which includes sawcutting of pavement at four inlet locations. Work along southbound Highway 1  will include installation of a light pole near the Log Cabin.


POSTED 3:39 PM PST, Friday, February 10, 2012 

Sunday Work, February 12
There is expected to be work on Sunday, February 12 during the day for slope stabilization and erosion control activities. The work will occur along southbound Highway 101, around the Ruckman Bridge, and in the construction staging areas adjacent to McDowell Avenue.


POSTED 4:45 PM PST, Thursday, February 09, 2012 

Night Work, February 9 and Saturday, February 11
There will be night work on Thursday, February 9 from 11:00 p.m. to 4:30 am. the next morning at the hook ramp and Ruckman Bridge to smooth out the new roadway.

There will be night work on Saturday, February 11 from 11:59 p.m. to 8:00 a.m. the next morning along southbound Highway 101/Doyle Drive near the Log Cabin. The work includes installing signage along the highway and requires a ramp closure of southbound Highway 101 to southbound Highway 1.


POSTED 2:37 PM PST, Tuesday, February 07, 2012 

Night Work – Highway 1 Lane Closures
Beginning Tuesday, February 7 for approximately two weeks there will be night work on and around the Ruckman Bridge due to required lane closures to grind, pave, stripe, remove temporary barriers and install electrical utilities and variable message signage along Highway 1 as part of the Highway 1/101 interchange improvements.

Night work hours will vary depending on the activity and lane closure restrictions. The longest work hours will be between 8:00 p.m. and 7:00 a.m.

Tentative work hours are:
February 7 & 8: 8:00 p.m. to 7:00 a.m.
February 9: 11pm to 4:30am
February 10: 11:59 p.m. to 5:00 a.m.
February 11: 11:59 p.m. to 8:00 a.m.
February 13: 11:00 p.m. to 4:30 a.m.
February 14 & 15: 8:00 p.m. to 7 a.m.
February 16: 11:00 p.m. to 5:00 a.m.

As part of this work, there is expected to be a full closure of northbound Highway 1 on the night of Friday, February 10 and a full closure of southbound Highway 1 on the night of Saturday, February 11. An advisory will be sent when the dates and times of these closures are confirmed.


POSTED 4:16 PM PST, Wednesday, February 01, 2012 

Night and Weekend Work – Hwy 1 Lane Closures
There will be night and early morning work on and around the Ruckman Bridge due to required lane closures to grind, pave, stripe and realign portions of Highway 1 as part of the Highway 1/101 interchange improvements.

  • Work is planned for 8 pm to 7 am on the following days:
    • Thursday, February 2
    • Friday, February 3
    • Sunday, February 5
    • Monday, February 6
  • On Saturday, February 4 and Sunday, February 5 from 5:00 am to 2:00 pm paving and striping will occur on northbound Highway 1.
In addition, a eucalyptus tree will be removed between the lower Storey residences and southbound Highway 1 on Thursday, February 2 during normal working hours. Removal of this tree will facilitate replacement of the lower Rod Road residential parking area.


POSTED 3:47 PM PST, Monday, January 09, 2012 

Lincoln Boulevard & Storey Avenue Closure and Night Work
The closure of Lincoln Boulevard and Storey Avenue has been extended and is expected to continue through the week of January 9 and potentially into the week of January 16. This closure is necessary to restore sidewalks and roadway elements in the area.

The lower portion of Storey Avenue is expected to remain closed approximately one week after Lincoln Boulevard re-opens. The website will be updated when the dates for these closures are confirmed.

Additionally, there is expected to be night work on Friday, January 20 and Saturday, January 21 from 7:00 p.m. to 10:00 a.m. the next morning. This night work is associated with closures of northbound and southbound Highway 1 at Highway 101 in order to shift the traffic alignment. An advisory will be sent with more information when the closure dates and times are confirmed. 


POSTED 12:21 PM PST, Tuesday, January 03, 2012 

Night Work along Southbound Highway 101 and Highway 1, January 3-5
As a reminder, there will be night work on Tuesday – Thursday, January 3-5, from 9:00 p.m. to 5:00 a.m. the next morning along southbound Highway 101 and Highway 1 to move temporary barrier railings (k-rail) and install light poles and signs.

This work must be conducted at night as it will require lane closures on Highway 1 and Highway 101.

The dates for this work could change depending on weather and unforeseen conditions.


POSTED 1:35 PM PST, Thursday, December 22, 2011 

Night Work for Ramp Closure and Alignment
On Tuesday, December 27 and Tuesday-Thursday, January 3-5, there will be work from 9 p.m. to 5 a.m. the next morning along southbound Highway 101 and southbound Highway 1 to work on the alignment of the off-ramp, remove temporary barrier railings (k-rail) and install crash cushions.

As part of this work, the ramp from southbound Highway 101 to southbound Hwy 1 will be closed on Wednesday, December 28 from 12:30 a.m. to 4:00 a.m.

The dates for this work could change depending on weather and unforeseen conditions.

There will be additional closures of Highway 1 in January as crews work to finalize the Highway 101/1 interchange. Advisories will be sent as dates and times are determined.


POSTED 2:07 PM PST, Friday, December 02, 2011 

Sunday Work for Light Pole Foundations, December 4
On Sunday, December 4 there will be work from 9 a.m. to 6 p.m. along southbound Highway 101 to southbound Highway 1 to install foundations for light poles.

Work will include pouring concrete, the use of heavy machinery and back-up beepers.

View the neighborhood letter for a map of the work area.


POSTED 10:19 AM PST, Monday, November 28, 2011 

UPDATE: Night Work for Toll Plaza Intersection Improvements
There is no night work scheduled for November 28 & 29 in association with the Golden Gate Bridge Southeast Visitor Plaza/Lincoln Boulevard/Merchant Road intersection improvement project.

There will be night work on Wednesday, November 30 for a concrete pour. There will be a closure of the last S.F. exit on Highway 101 in conjunction with this work.

We will update this page as future night work is scheduled.


POSTED 12:38 PM PST, Wednesday, November 16, 2011 

Night Work Along Highway 101, November 18
On Friday, November 18, there will be night work from 10 p.m. to 8 a.m. to shift the traffic alignment along the ramp from southbound Highway 101 to southbound Highway 1. Work will include minor paving, moving temporary barrier railing, and striping.

This work will require the closure of the off-ramp from southbound Highway 101 to southbound Highway 1.

This work and closure are weather dependent and could be rescheduled due to rain. The alternate date for the work is Saturday, November 19.


POSTED 11:41 AM PST, Wednesday, November 16, 2011 

Night Work for Toll Plaza Intersection Improvements
Due to traffic and safety concerns, the work to improve the northbound toll plaza off-ramp and the southeast Visitor Plaza/Lincoln Boulevard/Merchant Road intersection must occur at night.

The project will be implemented for approximately three weeks (weather permitting), beginning Wednesday, November 16. Work hours are 7 pm to 5 am each work night. There will be a detour in place, except during ramp closures referenced below. Please see the neighborhood letter for the detour route. Work will not occur over Thanksgiving weekend.

We apologize for the disruption associated with this work.


POSTED 1:27 PM PST, Friday, November 11, 2011 

Night Work for Intersection Improvements, November 16 & 17
Beginning Wednesday, November 16, for approximately three weeks there will be work at the Golden Gate Bridge Southeast Visitor Plaza/Lincoln Boulevard/Merchant Road intersection in order to improve traffic flow in the area. The majority of this work will occur between 7 a.m. and 7 p.m., however, there will be several nights of work associated with this project.

On Wednesday, November 16, and Thursday, November 17, work will occur from 10 p.m. to 5 a.m. to remove existing curbs, set barrier railing and demolish the existing median. This work will include saw-cutting, backfilling and the use of heavy machinery. During this time, the last exit on northbound Hwy 101 just before the Toll Plaza will be closed. See the advisory for a map with detour routes.

*Important changes to circulation* During this closure, there will be no access to Lincoln Boulevard from northbound Highway 101.


POSTED 2:26 PM PST, Wednesday, November 09, 2011 

Night Work Adjacent to Southbound Hwy 101 for Utility Installation
The night work previously scheduled for October 14 through October 31 was rescheduled to begin on Monday, November 14. This work is expected to last approximately one week and may continue through November 23 depending on weather.

The work will occur between the Log Cabin and the Toll Plaza and will include the use of heavy machinery to backfill the utility trench and restore the slope along the highway.

Work hours are 10 p.m. to 5 a.m.

This work will be conducted from the highway and must occur at night as it requires the closure of a lane on southbound Highway 101.


POSTED 9:16 AM PST, Monday, November 07, 2011 

Storey Avenue Closed at Lincoln Boulevard, Beginning Monday, November 7
Beginning Monday, November 7 for approximately one week, Storey Avenue will be closed at Lincoln Boulevard. The road closure hours may extend from 7 a.m. to 7 p.m. each day. This closure is necessary for crews to demolish the temporary widening section on the northbound Ruckman Bridge. This work will include the use of heavy machinery and hauling of debris.


POSTED 2:58 PM PST, Thursday, October 27, 2011 

Night Work Along Highway 1
On Friday, October 28 there will be night work from 8 p.m. to 7 a.m. on Highway 1 near the Ruckman Bridge to pour a section of the median barrier. Work will include pouring concrete and use of heavy equipment. The inside lanes of northbound and southbound Highway 1 will be closed during this activity.

On Friday, November 4 and Saturday, November 5, there will be night work from 10 p.m. to 8 a.m. to shift the traffic alignment of southbound and northbound Highway 1 and make room for installation of the permanent barrier railing. Work will include paving, moving temporary barrier railing, and striping. This work will require the closure of northbound Highway 1 on Friday night and southbound Highway 1 on Saturday night.

After the traffic shift, there will be future demolition work on the temporary widening section of northbound Highway 1. This is expected to occur during the day for approximately one week and will include a closure of Storey Avenue at Lincoln Boulevard. Dates for this work will be announced when they are scheduled, likely in early November.

Additionally, beginning in early/mid November there will be a closure of Lincoln Boulevard between Storey Avenue and Crissy Field Avenue to restore the alignment of the roadway. This will be a 24-hour closure and will last approximately three weeks. An advisory will be sent when the dates for this work are determined.


POSTED 10:25 AM PST, Tuesday, October 25, 2011 

Girard Road Extension, Beginning November 1
Beginning the week of November 1, crews will be working on Girard Road near the Swords to Plowshares building to construct a roadway extension to Gorgas Avenue. This extension will improve circulation in the area in preparation for the closures of Halleck and Marshall Streets in early 2012.

This work is expected to last three days and will include removing concrete bollards, grading, paving, and striping of the new roadway segment. Work hours will be 7:00 a.m. – 7:00 p.m.

There will be limited parking impacts to the southeast portion of the Swords to Plowshares parking lot.

View the advisory for a map of the work area.


POSTED 2:58 PM PST, Friday, October 21, 2011 

Sunday Work for Roadway Paving
On Sunday, October 23 there will be work from 8 a.m. to 4 p.m. for paving of the final alignment for the SB Highway 101 to SB Highway 1 off-ramp.

Work will include the use of heavy machinery and back-up beepers.

View a map of the work area.


POSTED 3:27 PM PST, Friday, October 14, 2011 

Night Work for Utility Installation, Beginning October 17
The night work for utility installation along southbound Highway 101 has been extended through the next two weeks. This work will occur between the Log Cabin and the Toll Plaza. 

The upcoming work will include the use of heavy machinery to backfill the utility trench and restore the slope along the highway.

Work hours will be 10 p.m. to 5 a.m.

This work will be conducted from the highway and must occur at night as it requires the closure of a lane on Highway 101.


POSTED 2:11 PM PST, Wednesday, October 05, 2011 

Night Work for Utility Installation, October 6 - October 14
Beginning Thursday, October 6 through Friday, October 14, there will be additional night work adjacent to southbound Highway 101 between the Log Cabin and the Toll Plaza for installation of electrical utilities which will power the new bridge and tunnel. Work will begin near the Toll Plaza and move east towards the Log Cabin.

The upcoming work will include the use of heavy machinery, trenching, and installation of utilities.

Work hours will be 9 p.m. to 5 a.m.

This work will be conducted from the highway and must occur at night as it requires the closure of a lane on Highway 101.


POSTED 3:57 PM PST, Friday, September 30, 2011 

Underground Utility Verification Work, October 5
On Wednesday, October 5, utility verification work will continue in the parking lot next to the YMCA pool. This work is in preparation for Phase II of construction of the Presidio Parkway, expected to begin in late 2011.

Work hours are expected to be 7:00 a.m. to 7:00 p.m., however, work is not expected to last the full day.

There are no anticipated parking or roadway impacts. Please follow the instructions of traffic controllers and signage.

View a printable advisory with a map of the work location.


POSTED 3:48 PM PST, Wednesday, September 28, 2011 

Night Work for Utility Installation, September 29 - October 5
Beginning Thursday, September 29 through October 5, there will be night work adjacent to southbound Highway 101 between the Log Cabin and the Toll Plaza to complete installation of electrical utilities.

Work will include the use of heavy machinery and backfilling of trenches with soil.

Work hours will be 9 p.m. to 5 a.m.

This work will be conducted from the highway and must occur at night as it requires the closure of a lane on Highway 101.


POSTED 9:25 AM PST, Wednesday, September 28, 2011 

Young Street and Parking Lot Closure, Beginning September 29
Young Street and the adjacent parking lot behind Building 201 will be closed beginning Thursday, September 29. This area will be gated at Halleck Street and used as a construction staging area to demolish Doyle Drive and build the rest of the project.

All vehicles must be removed prior to the lot closure on Thursday.

Thank you for your cooperation.

View a printable version of this notice, including a map.


POSTED 8:07 AM PST, Tuesday, August 09, 2011 

Underground Utility Verification Work, August 2011
Beginning August 11 and lasting approximately one week, utility verification work will continue in the Sports Basement parking lot and along Halleck Street and Lincoln Boulevard (see map below for locations). This work is in preparation for Phase II of construction of the Presidio Parkway, expected to begin in late 2011.

Work hours are expected to be Monday – Friday, 7:00 a.m. to 7:00 p.m.

There will be occasional one-lane traffic control and parking impacts at some sites. Please follow the instructions of traffic controllers and signage. No full road closures are anticipated.

See the advisory for a map of the work areas.


POSTED 3:13 PM PST, Thursday, August 04, 2011 

Night Work for Clearing, Trenching, Tree Removal and Utility Installation
Beginning Friday, August 5 through early September, there will be night work adjacent to southbound Highway 101 between the Log Cabin and the Toll Plaza.

Work will include clearing and grubbing, trenching, tree removal and the installation of electrical utilities.

Work hours will be 11pm to 7am on weekends and 10pm to 4:30am on weekdays.

This work will be conducted from the highway and must occur at night as it requires the closure of a lane on Highway 101.

Removal of these trees is necessary to install a new electrical line that will provide power to the new bridge, tunnel, and roadway.

Some of the larger trees will be preserved by hand trenching underneath the root systems.


POSTED 11:17 AM PST, Thursday, July 28, 2011 

Night Work for Bypass Paving, July 29, August 1, 2
Beginning at 6:00 p.m. and continuing until 8:00 a.m. the next morning on Friday, July 29, Monday, August 1 and Tuesday, August 2, there will be night work to pave the temporary bypass between the Main Post and Palace of Fine Arts.

Work will include increased truck traffic, delivery of materials and the use of back-up beepers and lights.

The temporary bypass will carry traffic beginning in late 2011 while the rest of the Presidio Parkway is built.

See a map of the paving areas.

We appreciate your patience during this activity.


POSTED 3:19 PM PST, Tuesday, July 26, 2011 

Night Work on Friday, July 29
On Friday, July 29, from 8 pm to 7 am the next morning, there will be work along northbound Highway 1/Park Presidio Boulevard near the Ruckman Bridge. Work will include trenching and the use of back-up beepers and lights to continue installing a drainage system.

During this work, one lane of northbound Highway 1/Park Presidio Boulevard to Highway 101/Doyle Drive will be closed.


POSTED 2:26 PM PST, Thursday, July 21, 2011 

Night Work and Storey Avenue Closure
* On Friday, July 22, from 11 pm to 5 am the next morning, there will be work along northbound Highway 1/Park Presidio Boulevard at the Highway 101/Doyle Drive interchange. Work will include trenching and the use of back-up beepers and lights to install a drainage system.

During this work, one lane of northbound Highway 1/Park Presidio Boulevard to Highway 101/Doyle Drive will be closed.

* Beginning Monday, July 25 through mid-August, Storey Avenue will be closed at Lincoln Boulevard (Ruckman Bridge) from 6 am to 5 pm daily. This closure is necessary to install a storm drain system and a sidewalk and curb.

* On Tuesday, July 26 from 1 am to 3 am, there is expected to be work to move k-rail along the ramp from southbound Highway 101/Doyle Drive to southbound Highway 1/Park Presidio Boulevard.

During this work, the connection from southbound Highway 101/Doyle Drive to Highway 1/Park Presidio Boulevard will be closed. This date is tentative; an advisory will be posted on the project website when the timing is confirmed.


POSTED 9:30 AM PST, Friday, July 08, 2011 

Night Work for Tree Removal Along Southbound Hwy 101/Doyle Drive
On Monday, July 11 and Tuesday, July 12 from 10 pm to 6 am, tree removal is planned to occur adjacent to southbound Highway 101/Doyle Drive.

This work must occur at night as it requires the closure of two lanes on southbound Highway 101.

Removal of these trees is necessary to install a new electrical line that will provide power to the new bridge, tunnel, and roadway.

See a map of the tree removal area.


POSTED 7:29 AM PST, Thursday, June 30, 2011 

Night Work for Large Concrete Pour, Thursday, June 30
There will be night work on Thursday, June 30 for a large concrete pour for the high viaduct. The pour will occur at the eastern end of the bridge near the opening of the southbound Battery Tunnel, and is scheduled to begin at 9:00 p.m. The pour is expected to last 8 to 10 hours.

See an aerial image of the work area.


POSTED 1:58 PM PST, Wednesday, June 29, 2011 

Tree Removal Along Southbound Hwy 101/Doyle Drive
This work has been postponed and is now expected to begin Tuesday, July 5.

Beginning Thursday, June 30, there will be tree removal work adjacent to southbound Highway 101/Doyle Drive. Work will begin near Upper Storey Avenue and will progress to the west adjacent to Highway 101. See the map for tree removal areas.

Removal of these trees is necessary to complete the new alignment for southbound Hwy 101/Doyle Drive to southbound Hwy 1/Park Presidio Boulevard.

See the letter to residents for a map of the tree removal areas.


POSTED 1:48 PM PST, Friday, June 24, 2011 

Sidewalk Replacement Beginning Tuesday, June 28
Beginning Tuesday, June 28 there will be sidewalk replacement work in front of 1273A and 1273B Ruckman Avenue. Activities will include concrete removal and replacement. Work will occur between 7 am and 5 pm and is expected to last three days.


POSTED 2:41 PM PST, Wednesday, June 22, 2011 

Night Work for Grading Along SB Hwy 101
On Wednesday, June 22 and Thursday, June 23 there will be night work along southbound Hwy 101/Doyle Drive near Storey Avenue in preparation for an upcoming traffic shift. Work is scheduled to last until midnight each night, and will include grading, material hauling and the use of back-up beepers.

There will also be night work and an overnight closure of the ramp from southbound Hwy 101 to southbound Hwy 1 on Friday, June 24 from 8:00 p.m. until 11:00 a.m. the next morning. Work during this time will include paving and installation of barrier railing. See the advisory for more information about this ramp closure.


POSTED 1:13 PM PST, Friday, June 17, 2011 

Storey Avenue Closure, Beginning June 17
Beginning Friday, June 17 for approximately two weeks, a full closure of Storey Avenue at Lincoln Boulevard will be required due to urgent work at the Ruckman Bridge. Storey Avenue will be closed 24 hours a day during this time.

Thank you for your continued patience during this work activity.


POSTED 9:59 AM PST, Thursday, May 26, 2011 

Start Time One Hour Earlier for Ruckman Bridge and Hook Ramp Work
Beginning May 31, construction activity is expected to begin at 6:00 am, Monday - Friday. Saturday work hours will remain 8:00 am – 6:00 pm. The early start time for this activity is expected to be in place through the end of June.

The additional hour of activity prior to regular working hours will be closely monitored and is required to meet specific sound limits. Sound monitoring equipment is in place and impactful work will be suspended if sound exceeds average ambient noise levels by more than 5 decibels. 

The next milestone will be to realign the off-ramp from southbound Highway 101 to Highway 1 and shift traffic to the new southbound Ruckman Bridge. This traffic shift is targeted for June 25 and will require an overnight closure of the southbound off-ramp and night work. The new southbound off-ramp and bridge will be two lanes. Notification with details will be sent closer to the date of the traffic shift.

We greatly appreciate your patience.


POSTED 2:24 PM PST, Monday, May 23, 2011 

Final Concrete Pour for Ruckman Bridge, 6:00 AM Start Time
On Tuesday, May 24, work will begin at 6:00 am for a concrete pour for the southbound Ruckman Bridge roadway deck. This is an important step towards finalizing the Ruckman Bridge.

The next milestone will be to realign the off-ramp from southbound Highway 101 to Highway 1 and shift traffic to the new southbound Ruckman Bridge. This traffic shift is targeted for June 25 and will require an overnight closure of the southbound off-ramp and night work. The new southbound off-ramp and bridge will be two lanes.  Notification with details will be sent closer to the date of the traffic shift.


POSTED 10:12 AM PST, Tuesday, May 17, 2011 

Utility Verification Beginning Week of May 16
Beginning the week of May 16 through early June, the project team will conduct utility verification along Gorgas Avenue, Thornburg Road, General Kennedy Avenue and O’Rielly Avenue. This work is necessary to prepare for Phase II of construction of the Presidio Parkway, expected to begin in late 2011.

Utility Verification Overview
To verify the utilities, crews will remove an approximately 10”x10” area of pavement using saw cutters or jack hammers and then use a vacuum truck to extract a soil sample. Upon completion, all holes will be backfilled and the work site will be restored to its original condition.

Work Hours
Work hours will be Monday – Friday, 7:00 a.m. to 7:00 p.m.

Traffic Control
One-way traffic control will be implemented, as needed. Please follow the instructions of traffic controllers and signage. No full road closures are anticipated.

Anticipated Timeline – May/Early June 2011

Upcoming work will occur near the following businesses/buildings:

• SenSpa
• Presidio Sport & Medicine
• YMCA
• Lucas Digital Arts
• Buildings on General Kennedy Avenue/O’Reilly Avenue

View the utility verification advisory, including a map.


POSTED 10:17 AM PST, Friday, May 13, 2011 

Night Work: Monday, May 16 at 11:59 p.m. to Tuesday Morning
There will be night work on Monday, May 16 starting at 11:59 p.m. for a large concrete pour for the hook ramp near the Hwy 101/Hwy 1 interchange. This concrete pour will require a lane closure on southbound Hwy 1 from 11:59 p.m. until 7:00 a.m. the next morning. The concrete pour and associated work will continue through Tuesday.

The use of backup beepers will be reduced to the greatest extent possible during nighttime hours. Lights will be directed away from homes.

Please see the advisory for the location of the concrete pour and staging area.

We apologize for the inconvenience. The project team has worked to avoid night work as much as possible to limit impacts to residents.


POSTED 3:39 PM PST, Thursday, April 28, 2011 

Night Work for Site Investigations, Week of May 2
From Monday, May 2 through Friday, May 6, there will be geotechnical site investigation work along the ramp from northbound Highway 1 to northbound Highway 101. Work hours are from  8 pm to 6 am the next day. This work will require a lane closure and must occur at night to avoid impacts to regional traffic.

This work is not expected to be noisy or bright.

See the neighborhood letter for a map of the activity.


POSTED 1:01 PM PST, Wednesday, April 27, 2011 

Utility Verification Work Beginning Week of April 25
Beginning the week of April 25 and continuing for approximately four weeks, there will be utility verification work around the eastern end of Doyle Drive. This work is in preparation for Phase II of construction of the Presidio Parkway, expected to begin in late 2011.

Utility Verification Overview
To verify the utilities, crews will remove an approximately 10”x10” area of pavement using saw cutters or jack hammers and then use a vacuum truck to extract the soil. Upon completion, all holes will be backfilled and the work site will be restored to its original condition.

Work Hours
Work hours are expected to be Monday – Friday, 7:00 a.m. to 7:00 p.m.

Traffic and Parking
There will be occasional one-lane traffic control and parking impacts at some sites. Please follow the instructions of traffic controllers and signage. No full road closures are anticipated.

View a printable advisory, including a map.


POSTED 9:25 AM PST, Tuesday, April 19, 2011 

Geotechnical Investigations Near Building 230 (Archeology Lab) - Week of April 18
There will be geotechnical investigations adjacent to the Archeology Lab, located at the intersection of Gorgas Avenue and Halleck Street, the week of April 18.

View the geotechnical investigation fact sheet.


POSTED 2:45 PM PST, Monday, April 18, 2011 

Geotechnical Investigations Near Gorgas Warehouses - Tentatively Begins April 20

There will be geotechnical investigation activity in the parking area behind the Gorgas Warehouses, adjacent to Richardson Avenue, beginning Wednesday, April 20 and continuing for approximately two weeks. Work is expected to occur Monday – Friday, between 7:00 a.m. and 7:00 p.m.

Each drill/test site will impact approximately five parking spaces and work at each site will last between two hours to one and a half days (no more than two drill sites will be impacted simultaneously).

Areas to be impacted will be identified in advance.

See the map for the specific drill/test locations.

After this work is complete there will be potholing to verify existing utilities in this area. Details to follow.

View a printable letter, including a map, regarding this work.

View the geotechnical investigation fact sheet.


POSTED 2:05 PM PST, Monday, April 11, 2011 

Night Work for Hook Ramp Construction Begins Tonight, April 11
Night work will begin tonight for hook ramp construction. The two shifts are expected to occur from 7 am – 1 am the next morning. The work schedule will be analyzed daily and night work will be avoided whenever possible.
 
In answer to some concerns raised by residents, we’d like to provide further clarification about the construction schedule for the hook ramp.  As construction began on the new the hook ramp in late 2010, the project encountered schedule delays primarily due to two factors: the presence of unknown utility lines and high groundwater conditions. Groundwater and surface runoff continued flowing during the month of March, causing the ground to be too saturated to allow work to begin until now.
 
To meet upcoming critical path milestones, it is necessary to expand the work schedule. However, we will do everything possible to mitigate impacts to residents during this time. We are working very closely with the contractor to minimize noise that may affect residents. Trucking, deliveries and back-up alarms will be minimized during night shifts. Concrete pours using large pump trucks will be scheduled during day shifts. The contractor's noise monitoring will continue in this area, and we will coordinate with Trust staff who will also be taking noise readings during this time.
 
To minimize impacts to nearby residents, noisier work activities will be scheduled during the day shifts.  In the event the sequencing of work would cause noisier work activities to occur at night, this work would be postponed and rescheduled to the next day shift. Saturday work shifts would be used to make up for lost night shifts.

Please check this page for updates on the night work schedule.

We appreciate your patience as we work to complete this critical portion of the project.


POSTED 12:31 PM PST, Monday, April 04, 2011 

No Double Shift Work Tonight for Hook Ramp Construction
There will be no double shift work tonight for hook ramp construction. The dates for double shifts are still being determined. We will distribute additional notification once the schedule has been finalized.

We thank you for your patience.


POSTED 9:33 AM PST, Thursday, March 31, 2011 

Extended Hours for Ruckman Bridge and Hook Ramp Construction
From Saturday, April 2 through late June, there will be extended work hours in order to make up for rain delays and to expedite completion of key elements of the Hwy 101/1 interchange. These extended hours will facilitate completion of this section of the project, including the Ruckman Bridge, the Hook Ramp (NB Hwy 101 to SB Hwy 1 connector ramp), and the realignment of southbound Hwy 101 to southbound Hwy 1.

Ruckman Bridge
Work hours for the Ruckman Bridge will be Monday to Friday, 7 am to 7 pm, and Saturday,  8 am to 8 pm. Storey Avenue will be closed during this activity.

Hook Ramp
Crews will be working double shifts on the Hook Ramp Monday to Friday, from 7 am to 1 am the next morning. Lighting will be directed away from homes.

We greatly appreciate your patience as we work to complete this critical portion of the project.

See the neighborhood letter for a map of the work areas.


POSTED 1:40 PM PST, Friday, March 25, 2011 

Sunday Work, March 27, and Potential for Extended Hours
There will be work this Sunday, March 27 from 9 am to 6 pm on the Ruckman Bridge. This is to continue falsework installation and is not expected to be disruptive. Storey Avenue will be closed during this activity.

This work is dependent on weather.

There is the potential for extended construction hours and future Sunday work in order to expedite completion of the Ruckman Bridge and portions of the new hook ramp. Additional notification will be provided when extended hours or Sunday work is confirmed.

See the neighborhood letter for a map of the work areas.


POSTED 4:02 PM PST, Wednesday, March 02, 2011 

Intermittent Traffic Control on Lincoln Boulevard
There will be intermittent one-way traffic control on Lincoln Boulevard between Crissy Field Avenue and Storey Avenue. This traffic control is necessary for on-going construction for the Ruckman Bridge replacement. 

We apologize for the inconvenience.

Please use caution in construction zones and follow directions from construction crews and signage.

See the advisory for a map of the location.


POSTED 3:32 PM PST, Wednesday, February 09, 2011 

McDowell Avenue Closed, Friday, February 11th, 2:00 - 5:00 a.m.
On Friday, February 11, McDowell Avenue will be closed from 2:00 to 5:00 a.m. for crews to reconfigure a crane boom. This work is not expected to be noisy.

Please see the map below for the closure location and detour route.

Please be cautious when traveling around construction sites and follow instructions from traffic controllers and on construction signage.

View the advisory for a map of the closure and detour routes


POSTED 3:04 PM PST, Wednesday, February 02, 2011 

McDowell Avenue Closed, Friday, February 4th, 2:00 - 6:00 a.m.
On Friday, February 4, McDowell Avenue will be closed from 2:00 to 6:00 a.m. for crews to finalize falsework for the southbound High Viaduct. This work is not expected to be noisy.

This falsework spans over the roadway and the road closure is required for traffic safety.

Please be cautious when traveling around construction sites and follow instructions from traffic controllers and on construction signage.

View the advisory for a map of the closure and detour routes.


POSTED 1:16 PM PST, Friday, January 14, 2011 

Early Morning Work for Large Concrete Pour, Wednesday, January 19
On Wednesday, January 19, work will begin in the early morning for a large concrete pour on the western  section of the new southbound bridge. Work will begin at 2 am and is expected to last throughout the day. Work must start in the early morning as a continuous operation is required to pour 1,500 cubic yards of concrete. Activities will include extensive truck traffic (approximately 150 trucks to deliver the concrete), equipment staging, associated noise, and back-up beepers.

This work will require intermittent traffic delays of approximately five minutes throughout the day on Lincoln Boulevard between Crissy Field Avenue and Storey Avenue.

Ongoing activity in the area includes the demolition of the old Ruckman Bridge to prepare for construction of the new southbound Ruckman Bridge. This demolition is expected to last through the month of January. The new bridge is expected to be complete in mid-2011.


POSTED 1:36 PM PST, Tuesday, January 11, 2011 

Double Shifts - Southbound Battery Tunnel Excavation
In order to increase the rate of tunnel excavation on the southbound Battery Tunnel, for the next two weeks crews are expected to resume working double shifts. Work hours will be 5 am to 1 am the next day. There is the possibility that this work will be extended to 24 hours a day.

There will also be significant truck traffic in the area in order to off-haul material. Trucks will exit out of the west end of the project on McDowell Avenue.

Please be aware that double shifts will occur intermittently for the next few months to expedite the completion of tunnel excavation.


POSTED 1:58 PM PST, Friday, January 07, 2011 

Night Work for Tree Removal North of Storey Ave/South of Hwy 101, January 11
On Tuesday, January 11, from 11:30 pm to 4:30 am the next morning, there will be nighttime removal of two trees adjacent to southbound Highway 101/Doyle Drive near the Log Cabin. This work cannot occur during the day due to traffic impacts on Highway 101.

Removal of these trees is necessary for future installation of an underground electrical line.


POSTED 3:08 PM PST, Monday, January 03, 2011 

Overnight Work to Conduct Highway 1 Traffic Shift at Ruckman Bridge
On Friday, January 7 and Saturday, January 8, there will be work along Highway 1 from 10 pm to 10 am the following morning in order to shift traffic onto a section of the new Ruckman Bridge and continue Highway 101/1 interchange improvements.

Tasks will include grading, paving, demolition of existing barrier rail, and installation of new barrier rail. The work on Friday will begin with demolition, which is likely the most noise producing phase of work. Demolition is expected to take approximately one hour to complete.

Ramp Closures between Highway 101/Doyle Drive and Highway 1/Park Presidio
• Northbound Highway 1 will be closed Friday, January 7 at 10 pm to Saturday, January 8 at 10 am (the closure will begin at Lake Street)
• Southbound Highway 1 will be closed Saturday, January 8 at 10 pm to Sunday, January 9 at 10 am

An advisory, including ramp closure details and detour routes, will be distributed this week.

Ongoing Activity
Upcoming construction in this area will involve demolition of the remaining old Ruckman Bridge and completion of the new Ruckman Bridge. This work is expected to occur during regular work hours,  7 am to 7 pm, and will require ongoing daytime closures of Storey Avenue at Lincoln Boulevard. The final bridge is expected to be complete in mid-2011.


POSTED 12:43 PM PST, Wednesday, December 01, 2010 

Intermittent Early Morning Traffic Control on McDowell Ave, December 2 and 3
There will be intermittent early morning traffic control on McDowell Ave from 2:00 – 7:00 am on Thursday, December 2 and Friday, December 3. Expect short delays on McDowell Avenue during this time.

Traffic control is necessary for falsework installation over the roadway for the southbound high viaduct.

Please be cautious when traveling around construction sites and follow the instructions from traffic controllers and construction signage.

We apologize for any inconvenience.


POSTED 3:13 PM PST, Friday, November 12, 2010 

Work 7 Days a Week for Southbound Battery Tunnel Excavation
Through the end of this year, crews will work seven days a week to complete the excavation for the southbound battery tunnel and install the necessary wall supports. The new weekend schedule, beginning Saturday, November 13, will be from 7 am to 7 pm, excluding Christmas Day and Thanksgiving.

The weekend work will be staged primarily at the west end of the project area near the National Cemetery in order to reduce impacts to the Riley neighborhood. Tunnel excavation is expected to be complete by the beginning of the new year.

As work progresses, we will provide updates about the schedule and project progress.

See the neighborhood letter for tunnel and retaining wall locations.


POSTED 3:01 PM PST, Friday, November 12, 2010 

Tonight: Night Work Along Northbound Hwy 1
There will be night work tonight, Friday, November 12, from 8 pm to 7 am the following morning along northbound Hwy 1 near the Hwy 1/Hwy 101 interchange for urgent underground utility work.

This work will require the closure of one lane of northbound Hwy 1 and must occur at night to avoid major traffic impacts. Work will include the use of back-up beepers.

We thank you for your patience and apologize for the inconvenience.


POSTED 10:13 AM PST, Wednesday, November 10, 2010 

Early Morning Work for Concrete Pours, November 12 and 16
Work will begin at 6:30 am on Friday, November 12 and at 6:00 am on Tuesday, November 16 in order to conduct large concrete pours for the new Ruckman bridge deck. 

We apologize for the inconvenience.


POSTED 1:34 PM PST, Friday, November 05, 2010 

No Night Work Friday and Saturday, November 5-6, Near Hwy 1/Hwy 101 Interchange
There will be no nightwork this Friday and Saturday, November 5-6, near the Hwy 1/Hwy 101 interchange. The work, initially scheduled for three nights, was completed in one night.

The connection from the Park Presidio Boulevard to the Golden Gate Bridge will be open this weekend.


POSTED 12:03 PM PST, Tuesday, November 02, 2010 

Night Work Near Hwy 1/Hwy 101 Interchange, November 4-5 (potential to extend)
Beginning Thursday, November 4 there will be at least one night of work near the Hwy 1/Hwy 101 interchange for crews to finalize the elevation of the falsework over northbound Hwy 1.

Work is scheduled:
- Thursday, November 4 at 11:59 pm to Friday, November 5 at 5 am

Only if needed, the work will continue for the following two nights:
- Friday, November 5 at 11:59 pm to Saturday, November 6 at 5 am
- Saturday, November 6 at 11:59 pm to Sunday, November 7 at 5am

The construction manager expects the work to be completed the first night. If there are unexpected conditions and the work needs to be extended, we will update this page of the website on Friday, November 5 before noon.

This work is not expected to be noisy.

Please note, the connection from northbound Hwy 1 to northbound Hwy 101 will be closed during this work. The closure will begin at Lake Street.

We thank you for your patience and apologize for the inconvenience.


POSTED 1:36 PM PST, Wednesday, October 27, 2010 

POSTPONED: Night Work Near Hwy 1/Hwy 101 Interchange, October 28-31
The night work scheduled for Thursday, October 28 through Sunday, October 31 near the Hwy 1/Hwy 101 interchange has been postponed until further notice.

A notice will be sent when the date for this night work is determined.

Thank you for your patience.


POSTED 12:20 PM PST, Friday, October 22, 2010 

Night Work Near Hwy 1/Hwy 101 Interchange, October 28-31
From Thursday, October 28 through Sunday, October 31 there will be three nights of work near the Hwy 1/Hwy 101 interchange for crews to finalize falsework installation over northbound Hwy 1.

Work will occur from:

- Thursday, October 28 at 11:59 pm to Friday, October 29 at 5 am
- Friday, October 29 at 11:59 pm to Saturday, October 30 at 5 am
- Saturday, October 30 at 11:59 pm to Sunday, October 31 at 5am

This work is not expected to be noisy.

Please note, the connection from northbound Hwy 1 to northbound Hwy 101 will be closed during this work. The closure will begin at Lake Street.

We thank you for your patience and apologize for the inconvenience.


POSTED 7:53 AM PST, Wednesday, October 13, 2010 

Storey Avenue Saturday Closures Starting October 16
The closure of Storey Avenue at Lincoln Boulevard will be extended to six days a week (including Saturdays) for the next couple months, starting this Saturday, October 16 (excluding October 23). Work will occur between 9 am and 6 pm.

The Saturday work and closures will allow crews to complete work on the Ruckman Bridge replacement before the rainy season begins.

We thank you for your patience and apologize for the inconvenience.


POSTED 11:42 AM PST, Friday, October 08, 2010 

Night Work Along Lincoln Boulevard Starting October 12
Beginning on Tuesday, October 12, night work will occur from 6 pm to 3 am along Lincoln Boulevard from Sheridan Avenue to Building 106. Crews will be installing a drainage line. The project in total will last approximately 3 weeks, with work progressing from west to east. However, work near Riley homes is expected to occur on approximately four nights beginning on Tuesday, October 12.

See the neighborhood letter for a map of the location.


POSTED 9:30 AM PST, Friday, October 01, 2010 

Night Work Near Building 106, October 4
On Monday, October 4 from 6:00 pm to 3:00 am there will be utility work along Lincoln Boulevard behind Building 106 in order for crews to complete portions of a temporary water line. The activity is not expected to be noticeable by Riley neighborhood residents.

This work must occur at night in order to avoid retaining wall work occurring during the day.

See a map of the night work area.


POSTED 1:16 PM PST, Friday, September 17, 2010 

Early Morning Truck Trips along Kobbe Avenue - September 22-25, 27-28
From Wednesday, September 22 through Tuesday, September 28 (excluding Sunday, September 26) two trucks per night will haul 105-foot-long beams along Kobbe Avenue between 3 am and 5 am. The trucks will be escorted by pilot cars.

These beams will be used to build the base for the temporary support structure that will span the pet cemetery in order to build the new southbound high viaduct. There will be early morning work in the Cavalry Stables area to off-load the beams.

The pet cemetery will be closed to the public from September 22 through late 2011.

See the advisory for a map of the truck route.


POSTED 9:12 AM PST, Wednesday, September 15, 2010 

Storey Avenue Saturday Closures, September 18 and 25
Please be advised that in addition to the Monday through Friday daytime closure already in place, there will be occasional Saturday closures of Storey Avenue at Lincoln Boulevard. Currently, there are closures scheduled for September 18 and 25, from 9 am to 6 pm. The Saturday work and closures will allow crews to work on the Ruckman Bridge replacement and maintain the project schedule.

We will keep you informed of additional Saturday closures as they are scheduled.

We apologize for the inconvenience.


POSTED 2:56 PM PST, Monday, September 13, 2010 

Double Shifts for Southbound Battery Tunnel Excavation Starting September 20
Major excavation for the southbound Battery Tunnel near the Riley Road neighborhood is expected to begin the week of September 20. In order to increase the rate of excavation prior to the rainy season, crews will resume working double shifts, from 5 am to 1 am the next day, Monday through Friday. There will also be significant truck traffic in the area in order to off-haul material.

Additionally, crews will start work on a retaining wall that will run along Lincoln Boulevard between Montgomery Street and Sheridan Avenue. This work will occur within normal construction hours: Monday to Friday from 7 am to 7 pm, and Saturday from 9 am to 6 pm.


POSTED 2:02 PM PST, Wednesday, September 08, 2010 

Early Saturday Work Hours (September 11) & Storey Avenue Closures
In order to install falsework over Storey Avenue for the new Ruckman Bridge, work is scheduled to begin at 7 am this Saturday, September 11. Storey Avenue will close at 7 am and reopen at 3:30 pm.

Additionally, due to the extensive work necessary to replace the Ruckman Bridge above Storey Avenue, the construction management team has determined that Storey Avenue will need to be closed at Lincoln Boulevard for the next six months, beginning Monday, September 13. The closure will be in effect Monday through Friday, 7 am to 5 pm. This will allow crews to complete the bridge efficiently and safely.

We apologize for the inconvenience and thank you for your patience during this activity.


POSTED 8:00 AM PST, Wednesday, August 25, 2010 

Storey Avenue Closed at Lincoln Boulevard, August 25 - September 10
Storey Avenue will be closed at Lincoln Boulevard from Wednesday, August 25 through Friday, September 10 in order to continue work on the Ruckman Bridge replacement.


POSTED 4:04 PM PST, Tuesday, August 24, 2010 

Tree Removal Near Storey Avenue Beginning Thursday, August 26
Beginning Thursday, August 26 through the week of Monday, August 30, construction crews will remove the first row of trees adjacent to southbound Highway 101/Doyle Drive, near Storey Avenue. Work will include tree removal, stump grinding, clearing and grading, and is expected to occur Monday-Friday, from 7am – 5pm. Additional fencing will be installed for visual screening and safety. Primary access to the tree removal and equipment staging areas will occur from the highway.

Removal of these trees allows for construction of the new hook ramp from northbound Highway 101/Doyle Drive to southbound Highway 1/Park Presidio Boulevard. The trees were originally scheduled for removal last summer, but this was postponed by construction management, in coordination with the Presidio Trust, in order to maintain the screening for residents as long as possible. The delay also allowed the removal equipment to be staged on the old highway instead of near the houses.


POSTED 10:41 AM PST, Thursday, August 19, 2010 

Lincoln Boulevard Partial Closure, August 23-25
From Monday, August 23 through Wednesday, August 25, Lincoln Boulevard will be closed each day from 7:00 a.m. to 3:00 p.m. between Storey Avenue and Crissy Field Avenue.

This closure is necessary in order to install falsework (temporary supports) for the new southbound high viaduct bridge.

Storey Avenue will remain open during this closure.

Vehicles should use Storey Avenue and follow detour signage back to Lincoln Boulevard. Pedestrians and bicyclists should use Long Avenue.

We apologize for the inconvenience associated with this closure.

View the advisory for more information and a map of the closure.


POSTED 1:36 PM PST, Wednesday, August 11, 2010 

Night and Morning Work: Saturday August 14 at 10pm – Sunday August 15 at 11am
Beginning Saturday, August 14 at 10 pm there will be night and early morning work on southbound Highway 101/Doyle Drive and the off-ramp to southbound Highway 1/Park Presidio Boulevard. This work is expected to be complete by 11 am the next day, Sunday.

Tasks will include pavement grinding, paving, and striping, as well as demolition of the existing and installation of a new barrier rail. This work is necessary to complete the Doyle Drive/Highway 101 alignment shift and continue Highway 101/1 interchange improvements.

In order to complete this work, the ramp from southbound Highway 101/Doyle Drive to southbound Highway 1/Park Presidio Boulevard will be closed. Please see the advisory for ramp closure details and detour route.


POSTED 8:02 AM PST, Thursday, August 05, 2010 

POSTPONED: Night Work: Saturday, August 7 ; Monday, August 9; Tuesday, August 10
The night work planned for Saturday, August 7, Monday, August 9, and Tuesday, August 10, on southbound Highway 101 and southbound Highway 1 in the area of the Highway 101/1 interchange has been postponed until further notice.

An update will be sent once this night work has been rescheduled.

We thank you for your patience.


POSTED 7:59 AM PST, Thursday, August 05, 2010 

Lower Storey Road Closure: Thursday, August 5 and the weeks of August 9 & 16
From Thursday, August 5 through Friday, August 20, the lower portion of Storey Avenue will be closed on weekdays at Lincoln Boulevard.  Please use upper Storey Avenue or Kobbe Avenue to access Lincoln Boulevard.

Please be aware that there will be intermittent closures of lower Storey Avenue until the new Ruckman Bridge is complete in approximately 6 months. Crews will post signs to inform residents of closure periods.


POSTED 2:19 PM PST, Friday, July 30, 2010 

Lower Portion of Storey Avenue Closed August 2 & 3, 7 am to 4 pm
On Monday, August 2 and Tuesday, August 3 from 7 am to 4 pm, the lower portion of Storey Avenue will be closed at Lincoln Boulevard for a large concrete pour of the new Ruckman Bridge abutment (where the bridge connects to the ground). Please use upper Storey Avenue or Kobbe Avenue to access Lincoln Boulevard.

All dates are subject to change due to weather and unforeseen conditions.


POSTED 8:58 AM PST, Tuesday, July 27, 2010 

Night Work for Roadway Maintenance
There will be night work July 27, 28 and possibly July 29 north of the MacArthur Tunnel and south of the Ruckman Bridge along Hwy 1 for roadway maintenance. There will be lane closures during this time.

This work is unrelated to the Presidio Parkway project.


POSTED 8:24 AM PST, Monday, July 26, 2010 

Extended Hours Starting July 26 for Battery Tunnel Construction
Work has begun on the southbound Battery Tunnel adjacent to the Riley neighborhood. Crews have removed the Lincoln Boulevard roadway bed next to the National Cemetery and have started drilling piles to support the new tunnel walls.

Beginning Monday, July 26, tunnel construction will require work to occur twenty hours per day, Monday to Saturday, until further notice. Construction hours will be from 5 am to 1 am (two 10-hour shifts).

Work on the tunnel will generally progress from west to east. Construction on the retaining wall will begin at a later date, and details will be provided as soon as they become available.

Noise readings were conducted during the week of July 5; results indicated that the work did not raise noise levels in the area significantly over ambient conditions. However, CalTrans project management will be actively working with the contractor to minimize impacts.

See the advisory for a map of tunnel and retaining wall areas.


POSTED 9:34 AM PST, Thursday, July 22, 2010 

Night Work, Thursday July 22 and Friday, July 23
On Thursday, July 22 and Friday, July 23 there will be night work in the area between northbound Highway 1 and southbound Highway 1 adjacent to Highway 101. Work will occur from 11 pm to 7 am.

Northbound Highway 1 will be closed at Lake Street from midnight to 5 am in order to stage vehicles for this activity.

We thank you for your patience during this work.


POSTED 2:50 PM PST, Wednesday, July 14, 2010 

Nightwork and Hwy 101 Lane Reduction, 10 p.m., July 17 - 8 a.m., July 18

There will be night work starting at 10 p.m. this Saturday, July 17 through 8 a.m. on Sunday, July 18 near the Hwy 1/Hwy 101 interchange as crews shift the roadway alignment to the north in order to make room for Highway 1/Highway 101 interchange improvements as part of the Doyle Drive replacement.

Shifting the roadway alignment will involve reducing traffic to one lane in each direction to allow for restriping and installing new holes for the lane change pylons (yellow barriers).

Lights will be directed away from homes during this activity.

View a printable advisory regarding the lane reduction, including a map.


POSTED 3:33 PM PST, Monday, July 12, 2010 

Early Morning Work, Tuesday, July 13 and Wednesday, July 14
There will be early morning work Tuesday, July 13, 2010 and Wednesday, July 14 in the area between northbound Doyle Drive and the Highway 1 on-ramp (see yellow area on the advisory below). Night work hours are expected to be 4:00 a.m. to 7:00 a.m.

Please see the July night work advisory for details.


POSTED 3:09 PM PST, Friday, July 09, 2010 

Early Morning Work, Monday, July 12, 2010
There will be early morning work Monday, July 12, 2010 in the area between northbound Doyle Drive and the Highway 1 on-ramp (see yellow area on the advisory below). Night work hours are expected to be 4:00 a.m. to 7:00 a.m.

Please see the July night work advisory for details.


POSTED 3:43 PM PST, Thursday, July 08, 2010 

Additional Night Work in July
Additional night work has been scheduled for the coming weeks as construction of the new Ruckman bridge and southbound high viaduct progresses.

Grading & Paving Adjacent to Northbound Hwy 101

There is night work scheduled in this area July 8 and 9 to prepare for a northbound traffic shift on Hwy 101 scheduled for mid-July.

There is also night work expected the week of July 19-23. More details will follow.

Temporary Bridge Support (Falsework) Installation - July 9 and 10

There will be night work July 9 and 10 in order to place the temporary bridge support (falsework) over Highway 1 for the new southbound high viaduct. This work will require a closure of northbound Hwy 1 between midnight and 5pm
in order to complete installation.

This work is not expected to be noisy.

Please see the advisory for more details.


POSTED 3:56 PM PST, Friday, June 25, 2010 

Night Work Update through July
Due to careful planning and off-peak lane closures, construction crews have been able to avoid the majority of previously planned night work and limit construction impacts to nearby residents.

There are still certain activities that may occur during nighttime hours in the coming weeks. As a reminder, night work is necessary when construction requires a highway lane closure that would cause region-wide traffic impacts or if the work activity is continuous and cannot be stopped, such as a concrete pour.

Upcoming night work includes:

Grading & Paving Adjacent to Northbound Highway 101 through Mid-July

The night work planned from June 14 through June 28 did not occur, as crews were able to conduct the work between 9:30 a.m. and 2:30 p.m.

However, intermittent night work may be necessary in this area over the next few weeks to prepare for a northbound traffic shift on Hwy 101 scheduled for mid-July.

Bridge Foundation & Column Work through July

Intermittent night work will continue in the Cavalry Stables area through July to finish bridge foundations and columns. There will be intermittent noise associated with machinery and generators. Lights will be directed away from homes.

For more information, please see the updated night work advisory.


POSTED 11:57 AM PST, Wednesday, June 23, 2010 

Demolition of Old Ruckman Bridge Underway
Demolition of the former northbound lanes of the Ruckman Bridge is currently underway. Watch it all on the webcam!

Please expect occasional closures of Storey Avenue during this activity. Signage will be in place.


POSTED 3:13 PM PST, Thursday, June 17, 2010 

Major Construction to Begin on the Southbound Battery Tunnel and Retaining Wall
Construction of the southbound Battery Tunnel and retaining wall adjacent to Riley Road is expected to begin tomorrow (Friday), June 18.

During the initial phase of construction, crews will remove the asphalt on the closed section of Lincoln Boulevard and begin drilling support foundations for the retaining wall and tunnel sections. You can expect to see an increase in construction activity, including equipment staging, truck and heavy equipment traffic, earthwork and grading, drilling, and concrete pouring.

As construction progresses, many activities must occur outside of regular working hours. Regular working hours are Monday to Friday from 7 am to 7 pm, and Saturday from 9 am to 6 pm.

Work may occur outside of regular hours when:
- it is determined that the noise created by the activity is within permitted ranges
- there is a highway lane closure that would cause region-wide traffic impacts
- there is continuous work that cannot be stopped, such as a concrete pour
- there is critical path work that would have significant schedule implications

When work outside of normal work hours near is expected, advance notification will be sent.


POSTED 1:23 PM PST, Thursday, June 17, 2010 

Utility Switch Over Complete
The utility switch over to transfer power to new electrical supply lines has been completed early. Service has been restored to the Ruckman, Storey, West Washington, Kobbe, and South Baker Beach neighborhoods.


POSTED 3:30 PM PST, Friday, June 11, 2010 

Power Outage - Thursday, June 17, 8 am to 5 pm
In recent weeks, new electrical supply lines serving the western areas of the Presidio have been installed. This utility work has been necessary to facilitate the reconstruction of the Doyle Drive roadway. The new equipment will result in a more stable and reliable power delivery system for Presidio residents and tenants.

In order to switch over to the new system, a one-time power outage affecting the Ruckman, Storey, West Washington, Kobbe, and South Baker Beach neighborhoods is scheduled for Thursday, June 17, from 8 am to 5 pm.

We greatly appreciate your patience as we complete this necessary work. Should any weather or project-related changes to the schedule occur, we will notify you as soon as possible. Please check this page for the most up-to-date information.


POSTED 9:57 AM PST, Thursday, June 10, 2010 

Night Work Update, June 2010
There will be various night work activities occurring in the southwest section of the project over the next few weeks. These include:

Grading & Paving Adjacent to Northbound Highway 101 through June

From June 14 through 28 there will be intermittent night work to realign northbound Highway 101 near the Park Presidio Interchange.

This work will require the use of heavy equipment, loading and dumping of material, grading, drainage installation, and paving.

Bridge Foundation & Column Work through July

Intermittent night work will continue in the Cavalry Stables area through July to create bridge foundations and columns. This work will include twisting steel casings into the ground, removing material inside the casings, welding and concrete pours. There will be occasional noise associated with machinery and generators. Lights will be directed away from homes.

Night Work for Northbound Ruckman Bridge Traffic Shift

Night work will occur Monday, June 14 through Friday, June 18 along Highway 1, under Highway 101, in order to prepare for the northbound Ruckman Bridge traffic shift. The traffic shift and associated ramp closure are expected to occur overnight on Friday, June 18. This night work was originally scheduled for the week of June 7 but was postponed.

For more information and a detailed map, view the advisory.


POSTED 1:36 PM PST, Monday, June 07, 2010 

Night Work POSTPONED
There will be no night work tonight, Monday, June 7.

The ramp closure preparation night work originally scheduled for tonight, June 7 through Thursday night, June 10 has been POSTPONED until next week, June 14-18. The ramp closure from northbound Highway 1/Park Presidio Boulevard to northbound Highway 101/Doyle Drive is now expected to occur on Friday, June 18 starting at 10 p.m.  Details to follow.

Some night work may be necessary this week. Please check the website for additional information as it becomes available.


POSTED 12:23 PM PST, Friday, June 04, 2010 

Night Work to Prepare for Northbound Traffic Shift, June 4 and 7-10
An overnight closure of northbound Highway 1 to northbound Highway 101 is expected to occur on June 12 to enable a shift of traffic on the Ruckman Bridge. In advance of this, nighttime work is needed tonight, Friday, June 4 and Monday, June 7 through the morning of Friday, June 11 along Highway 1, under Highway 101.

Night work hours are 8 pm to 7 am.

Residents can expect a similar level of activity as occurred last night, Thursday, June 3. Construction noise was measured on June 3 and found to be slightly above normal (ambient) conditions typical to the area.


POSTED 9:48 AM PST, Thursday, June 03, 2010 

Night Work and Sunday Construction Scheduled This Week
There will be night work tonight, June 3, for crews to perform finishing work in the area of northbound Hwy 1 adjacent to Hwy 101.

There is also Sunday work scheduled for June 6 from 9 a.m. to 6 p.m. in this area.


POSTED 2:02 PM PST, Wednesday, May 26, 2010 

Night Work for Median Demolition Beginning June 1
In order to shift northbound traffic lanes to the west to start reconstruction of the Ruckman bridge, portions of the median barrier on Highway 1 need to be demolished.

The median demolition is scheduled to take place from the evening of Tuesday, June 1 through the morning of Friday, June 4.  

Night work hours are 8 pm to 7 am.

This work must occur at night as it requires lane closures on southbound and northbound Highway 1.

This demolition work is expected to be very noisy, and will require the use of heavy equipment and demolition of concrete, as well as the use of back-up beepers. We apologize for the disruption and thank you for your patience.

View a printable advisory regarding upcoming night work activities.


POSTED 3:27 PM PST, Monday, May 24, 2010 

McDowell Avenue & Mason Street Resurfacing, Week of May 24
During the week of May 24, roadway resurfacing work will occur on Mason Street and McDowell Avenue. There will be traffic control and closures associated with this work. Targeted dates and roadway impacts include:

Tuesday, May 25: Expect occasional delays on Mason Street and McDowell Avenue.

Wednesday, May 26: McDowell Ave will be closed.

The PresidiGo Around the Park Shuttle stops 6, 7 and 8 will not be available during this closure.

Access to the U.S. Park Police Stables and the Park Archives building will be provided via Lincoln Boulevard to McDowell Avenue.

Thursday, May 27 and Friday, May 28: There will be one lane traffic control on Mason Street from Halleck Street to Crissy Field Avenue.

This activity is reliant on dry weather. All dates are subject to change due to rain and unforeseen conditions.

View a printable advisory, including a map of the closure location and detour routes.


POSTED 8:25 AM PST, Monday, May 24, 2010 

May 2010 Construction Look Ahead
Construction of the next major component of the Presidio Parkway Project - the southbound Battery Tunnel and a temporary bypass - will begin in late May 2010 and continue through late 2011.

You can expect to see the following upcoming activities as this new phase of the project gets underway.

1. Resurfacing of McDowell Avenue, Mason Street and Halleck Street ~ Week of May 24, 2010
2. Lincoln Boulevard Closes between McDowell Avenue and Montgomery Street ~ Late May/Early June, 2010 – Late 2011
3. Construction Fence Installation and Parking Impacts ~ Late May/Early June 2010
4. Demolition of Buildings 605 & 606 (formerly Public Storage) ~ June 2010

Click here to access the printable advisory for maps and additional information.


POSTED 3:32 PM PST, Tuesday, May 18, 2010 

Overnight Ramp Closure Beginning May 21 at 10 p.m.
In order to transfer traffic to the new temporary bridge on Highway 1, north of the MacArthur Tunnel, the southbound ramp from Hwy 101/Doyle Drive to Hwy 1/Park Presidio Boulevard will be closed from Friday, May 21 at 10:00 p.m. through Saturday, May 22 at 10:00 a.m.

This traffic shift and short-term ramp closure will allow traffic to continue to flow unimpeded while the permanent bridge is built.

Motorists should be aware of the new roadway configuration and use caution in construction zones.

View a printable advisory, including a map.

View the animation of the traffic shift.

See it on our webcam!

Ramp Closure Detour

View a map and directions for the detour route


POSTED 3:33 PM PST, Friday, May 14, 2010 

Night Work Rescheduled - Overnight Ramp Closure Now May 21
Please be aware that on Friday, May 21 at 10:00 p.m. through Saturday, May 22 at 10:00 a.m. there will be extensive construction in order to shift southbound traffic to the temporary Ruckman Bridge.

This work will include asphalt grinding and demolition, paving, placement of traffic barriers (K-rail), and striping. This activity is expected to be noisy and will require the use of heavy equipment and back-up beepers. Lights will be directed away from homes.

Please note the contractor will make every effort to expedite the work and complete the traffic tie-in as quickly as possible.

All dates are subject to change due to weather and unforeseen conditions.


POSTED 2:30 PM PST, Thursday, April 29, 2010 

McDowell Avenue Closed, Starting 3 p.m., Friday, April 30
McDowell Avenue will be closed starting at 3 p.m. Friday, April 30 for 12-16 hours for a large concrete pour for one of the 12’ diameter bridge piles (column foundation). There will be significant truck traffic associated with this work.

McDowell Avenue will reopen upon completion of this operation.

The PresidiGo Around The Park Shuttle stops 6, 7 and 8 will not be available during this activity.

View the advisory for closure location and detour routes.


POSTED 8:02 AM PST, Friday, April 23, 2010 

Presentation from April 20 Parkwide Meetings
The presentation from the April 20 Presidio resident and tenant project update meetings is now available in the Public Meeting Materials section of the website. This presentation discusses work completed to-date and upcoming construction milestones.

View the project update meeting presentation.


POSTED 3:44 PM PST, Tuesday, April 20, 2010 

POSTPONED: April 23 Overnight Ramp Closure and Associated Night Work
The previously scheduled night work associated with the closure of the southbound ramp from Highway 101 to Highway 1 has been postponed until further notice.

We apologize for the change in schedule. We will post information on this page and send an e-mail notice when a new date for this closure and night work is scheduled.


POSTED 12:03 PM PST, Friday, April 16, 2010 

Night Work Associated with Overnight Ramp Closure, April 23
Please be aware that on Friday, April 23 at 10:00 p.m. through Saturday, April 24 at 10:00 a.m. there will be extensive construction in order to shift southbound traffic to the temporary Ruckman Bridge.

This work will include asphalt grinding and demolition, paving, placement of traffic barriers (K-rail), and striping. This activity is expected to be noisy and will require the use of heavy equipment and back-up beepers. Lights will be directed away from homes.

Please note the contractor will make every effort to expedite the work and complete the traffic tie-in as quickly as possible.

All dates are subject to change due to weather and unforeseen circumstances.

View the printable advisory regarding the ramp closure.


POSTED 1:21 PM PST, Tuesday, April 13, 2010 

Night Work in Cavalry Stables Area
There will be intermittent night work this week in the Cavalry Stables area to create bridge foundations.

View the advisory update, including activities and work areas.

Please continue to check this page or call (415) 263-5953 for night work updates.

 


POSTED 8:54 AM PST, Monday, April 12, 2010 

Project Update Meetings for Presidio Residents and Tenants, Tuesday, April 20
Construction of the Presidio Parkway, the Doyle Drive replacement, is in full swing. The project team will be holding two meetings on Tuesday, April 20 to discuss what is ahead in the construction process and answer questions.

Tenants Meeting
Tuesday, April 20, 2010
12:00 p.m. – 1:00 p.m.

Residents Meeting
Tuesday, April 20, 2010
6:30 p.m. – 8:00 p.m.

Both meetings will be held in the Cypress Room of the Golden Gate Club at 135 Fisher Loop.

View the meeting flyer for more details.


POSTED 1:10 PM PST, Friday, April 09, 2010 

Bridge Pile (Foundation) Work through June
There will be intermittent night activity in the Cavalry Stables area through June to create bridge foundations. Beginning Monday, April 12, work will include twisting steel casings into the ground, removing material inside the casings, welding and concrete pours. There will be intermittent noise associated with machinery and generators. Lights will be directed away from homes.

Updates will be posted as the specific schedule of night work is determined.

View the advisory update, including activities and work areas.


POSTED 1:31 PM PST, Wednesday, April 07, 2010 

Night Work Update: April 7, 2010
No night work is scheduled for the week of April 5.

Please continue to check this page or call (415) 263-5953 for night work updates.


POSTED 2:22 PM PST, Friday, April 02, 2010 

Night Work Update: April 2, 2010
Night work has been canceled for Friday, April 2. Dates for future night work activities are to be determined. We will update the web site and outgoing phone message once it is determined if night work is necessary.

View the advisory update, including activities and work areas.

Please check our Web site and subscribe to this RSS feed at www.PresidioParkway.org/neighbors or call our project information line at (415) 263-5953 for the most up-to-date information regarding night work.


POSTED 2:29 PM PST, Tuesday, March 30, 2010 

Night Work Update: March 30, 2010
Night work has been canceled for Tuesday, March 30, Wednesday, March 31 and Thursday, April 1. There is a possibility that night work will occur on Friday, April 2. We will update the web site and outgoing phone message once it is determined if night work is necessary.

Please check our Web site and subscribe to this RSS feed at www.PresidioParkway.org/neighbors or call our project information line at (415) 263-5953 for the most up-to-date information regarding night work.


POSTED 9:57 AM PST, Monday, March 29, 2010 

Night Work Update: March 29, 2010
Night work has been canceled for Monday, March 29 and will likely be canceled for the remainder of the week.

Please check our Web site and subscribe to this RSS feed at www.PresidioParkway.org/neighbors or call our project information line at (415) 263-5953 for the most up-to-date information regarding night work.


POSTED 10:43 AM PST, Tuesday, March 23, 2010 

Schedule of Upcoming Night Work: March 23 - April 2
Previously announced night work is CANCELLED for March 24 and 25.

Night work is scheduled Monday through Thursday during the week of March 29.

Night work is planned near the Park Presidio Interchange Monday through Thursday the week of March 29, for grading and embankment construction to temporarily realign northbound Highway 101.

This work will require the use of heavy equipment, loading and dumping of material, as well as the use of back-up beepers.

Please note, the contractor will make every effort to expedite the work and reduce the amount of night work whenever possible.

Please call (415) 263-5953 with any questions.

View the printable advisory, including dates and work areas.


POSTED 2:34 PM PST, Friday, March 19, 2010 

Intermittent Night Work through June 2010
Intermittent night work will occur in the western area of the project from the week of March 22 through June 2010. This night work is necessary when construction requires a highway lane closure or continuous work activity, such as a concrete pour.

These activities are not permitted to occur during the day because lane closures would cause regionwide traffic impacts.

The contractor will make every effort to expedite the work and reduce the amount of night work whenever possible.

View the printable advisory, including dates and work areas.


POSTED 2:59 PM PST, Friday, December 11, 2009 

McDowell Avenue Utility work Extended to January 4, 2010 - McDowell Avenue Closed December 16-18
Utility relocation activity on McDowell Avenue has been extended and is expected to occur through
January 4.

From December 16 through 18, McDowell Avenue will be closed and vehicles will be detoured to Halleck
Street to access Mason Street. Crissy Field businesses will remain open.
 
During the road closure, the PresidioGo Around The Park route stops 6, 7 and 8 will not be
available.

Access to the U.S. Park Police Stables and the ParkArchives building will be provided via Lincoln Boulevard to
McDowell Avenue.

One way traffic control is expected until January 4 for utility installation, trench backfilling, and repaving.

Click here to view the advisory including a map and detour routes.


POSTED 2:40 PM PST, Monday, November 30, 2009 

McDowell Avenue Closed November 30 to December 11, 2009
Monday, November 30 through Friday, December 11, McDowell Avenue will be closed for utility relocation activities.

This activity will impact Muni service and the PresidiGo Around The Park Shuttle service. Specifically, Muni Route 29 will not be available on:

  • McDowell Avenue
  • Eastbound Mason Street between Crissy Field Avenue and Halleck Street
  • Southbound Halleck Street
  • Westbound Lincoln Boulevard between McDowell and Crissy Field Avenue
The PresidioGo Around The Park route stops 6, 7 and 8 will not be available.

Access to the U.S. Park Police Stables and the Park Archives building will be provided via Lincoln Boulevard to McDowell Avenue.

Click here to view the advisory including a map and detour routes.


POSTED 9:15 AM PST, Monday, November 02, 2009 

Utility Relocation Work Through February 2010
Utility relocation activity in the vicinity of McDowell Avenue and Lincoln Boulevard is underway and will be complete in late November 2009.

Utility relocation along Mason Street and adjacent to Lincoln Boulevard (near the San Francisco National Cemetery) will begin the week of November 2, 2009 and continue through February 2010. Work will progress west to east.

View the utility relocation advisory


POSTED 10:01 AM PST, Thursday, September 24, 2009 

FINAL WEEKEND CLOSURE OF RAMPS TO SOUTHBOUND HWY 1/PARK PRESIDIO, September 26-27 from 5:30-11:30 a.m.
The off-ramps from Highway 101/Doyle Drive to southbound Highway 1/Park Presidio Boulevard will be closed this Saturday and Sunday from 5:30-11:30 a.m.

This is the fourth and final weekend morning ramp closure necessary to safely conduct tree removal adjacent to the ramps in preparation for construction of the Doyle Drive replacement.

Northbound Highway 1 to the Golden Gate Bridge and southbound Highway 1 in San Francisco will remain open. Those traveling from the North Bay to the San Francisco International Airport should use Highway 101.

Weekend morning closures of southbound Highway 1 ramps will:
•    Ensure tree work can be conducted safely and when traffic volumes are low
•    Avoid impacts to weekday commute traffic

View a printable version of this advisory, including closure and detour maps.
View photos from the initial weekend ramp closure tree removal on August 22 – 23.


POSTED 2:28 PM PST, Tuesday, August 18, 2009 

Utility Work Near Kobbe Neighborhood to Begin the Week of August 17, 2009
Utility relocation work will begin the week of August 17 to relocate gas lines in the vicinity of Park Boulevard, Hitchcock Street, and McDowell Avenue.

Temporary service interruptions will be required, and PG&E will follow their standard notification procedures, which include a 10-day advance notice to customers.

Work in this area is expected to last approximately two months. Hours of operation will be 7 a.m. to 7 p.m. weekdays, and 9 a.m. to 6 p.m. on Saturdays. Potholing and trench-less utility installation equipment will be used to minimize impacts to residents.

While one-lane traffic control may occasionally be required during this work, access to Hitchcock Street and Kobbe Avenue will be maintained. Parking will not be impacted.


POSTED 10:43 AM PST, Monday, August 10, 2009 

Utility Relocations - Late August 2009
Utilities in the project corridor, including potable water, sanitary sewer, telecommunications and electrical will be relocated beginning in late August.

Advisories and details about work locations will be available here.


POSTED 9:41 AM PST, Monday, August 10, 2009 

Tree Removal
To construct the new roadway and create space for construction activities, the area surrounding the construction site must be carefully cleared prior to construction. Tree removal began on Tuesday, August 11 and will continue through October 2009.

View the notice sent to residents and tenants.

Click here to view the public notice.


POSTED 8:58 AM PST, Monday, November 02, 2009 

Nov. 12 & 16 - Learn More About the First Phase of Construction, Beginning in November 2009.

Commercial Tenant & Employee Meeting

Thursday, November 12, Noon to 1:30 pm
Golden Gate Club, Cypress Room
135 Fisher Loop
San Francisco, CA 94129

Resident Meeting

Monday, November 16, 6:30 to 8:30 pm
Golden Gate Club, Cypress Room
135 Fisher Loop
San Francisco, CA 94129


POSTED 8:35 AM PST, Wednesday, October 21, 2009 

Marina, Richmond, and Marin Meetings
You are invited to attend one of the upcoming community meetings to learn more about the construction of this important infrastructure project, traffic details, as well as the associated ramp closures necessary to construct the western portion of the new roadway.

Richmond Neighborhood
Thursday, October 29, 2009
6:00-7:30 p.m.
Self-Help for the Elderly
408 22nd Avenue (at Geary Boulevard) map
San Francisco, CA 94121
 
Marin
Monday, November 2, 2009
6:00-7:30 p.m.
Redwood High School
395 Doherty Dr., Larkspur, CA 94939 map

Marina Neighborhood
Wednesday, November 4, 2009
6:00-7:30 p.m.
Fort Mason Center, Golden Gate Room map
Landmark Building A Conference Center
San Francisco, CA 94123


 

 